SMEC and Arcadis are currently engaged by Laing O’Rourke in a fully integrated Design Joint Venture (DJV) to deliver the initial and early works design for Victoria’s Suburban Rail Loop (SRL) East. The engagement brings SMEC’s extensive experience working across complex multidisciplinary design projects to assist Laing O’Rourke and Suburban Rail Loop Authority in successfully delivering transformative infrastructure to the community.

Connecting Melbourne’s suburbs

 

The SRL project will ultimately deliver a 90km rail line linking every major line from Frankston to Werribee via the Melbourne Airport, and is divided into four key stages – SRL East, North, Airport and West. Three transport super hubs to be developed in Clayton, Broadmeadows and Sunshine will better connect Victorians to jobs, retail, education, health services and each other.

 

Construction is underway on the initial and early works for the first phase, SRL East, including the site establishment for six new stations and a stabling area, tunnel access shafts, road and tram diversions and relocating major utilities from the main works areas.

 

The forward-thinking early works design by technical specialists from SMEC will critically support the successful and timely implementation of the first phase of works.

 

The early works design includes flood modelling, hydrogeology modelling, earthworks and grading, traffic modelling & road diversions, combined non-contestable service routing, sewer and water mains design, bridge structures, tunnel access shafts, geotechnical structures and foundations, tram works, earthing and bonding and system and safety assurance.

 

“SMEC are excited about being part of reshaping Victoria’s Public Transport Network for the future, transforming the way people move and better connecting communities. It’s great to see the project progress from concept through to construction and we look forward to supporting the successful delivery of Suburban Rail Loop’s first phrase by ensuring our design and design team remains forward-thinking and adaptable across all stages”
— Derek Frend, SMEC Executive Project Manager.

Collaborative teamwork vital to success

 

The SRL project is a hugely complex disaggregated program of work with multiple interactions between packages. The Initial and Early Works package has critical interfaces with the two Tunnelling Packages (Major Works) which progressed through procurement in parallel with the implementation of Initial and Early Works design development.

SMEC were able to provide not only key designers for the project, but also turnkey integrated modelling, including:

  • CAD/Digital Engineering
  • 12d design
  • Flood and hydrogeology modelling
  • Traffic modelling (road and specialist VISSIM tram interface modelling).

With Laing O’Rourke, SMEC and Arcadis continue to work closely with SRLA to deliver change and additional services to simplify the interfaces between packages, address key issues and ensure a smooth transition from Initial and Early Works and Major Works.  These changes include, amongst other things:

  • Minimising any service relocation for Major Works
  • Design refinement for the tunnel access shafts
  • Developing design for the TBM Bulk Power Supplies
  • Supporting the inclusion of innovative Tunnel Access Structures and associated design development.

 

Key milestones


SRL East will be open by 2035, delivering better transport connections, slashing travel times and creating a pipeline of jobs and training opportunities.

The design of the Initial and Early Works has been specifically prioritised to ensure a smooth transition from Initial and Early Works and Major Works. Specifically, the two Tunnel Access shafts will be completed in accordance with the Major Works need.

The inclusion of TBM Bulk Power Supply design will also enable the Major Works contractor to essentially ‘plug and play’ with the TBMs when they are delivered to site.

In a key sustainability milestone, all flood and hydrogeology modelling were required to consider the project impact, given the current climate challenge and with a 100 year lookahead.

26
km
underground rail line from Cheltenham to Box Hill
6
Stations/Precincts – Cheltenham, Clayton, Monash, Glen Waverley, Burwood and Box Hill
1
Stabling Yard